South Philadelphia, PA · April to August 2025
South Philadelphia rowhome: full renovation, April to August 2025
A brick rowhome taken down to the studs in April and handed back in August. New kitchen, two bathrooms, a rebuilt staircase with iron balusters, vinyl plank floors throughout, a finished basement, new windows, a new front door and a cedar-fenced patio.
South Philadelphia, PAAug 2025afterBefore and after


Scope
What we did
Services on this job: whole-home renovation, kitchen remodeling, bathroom remodeling, stairs and railings, basement finishing, flooring and tile, windows and doors, siding, fences and exterior, interior and exterior painting, drywall repair.
- Demolition of the first floor and the old staircase
- New stair stringers, oak treads, painted risers, iron balusters
- Kitchen: white shaker cabinets, quartz counters, tile backsplash
- Two full bathrooms: marble-look tile tub bath and grey tile glass shower
- Vinyl plank flooring on the living floors, carpet in the basement
- Finished basement with drop ceiling and closets
- Replacement windows and new entry door, iron railings
- Cedar privacy fence, stained planter, concrete patio
- Drywall and paint throughout
The house
A two-story brick rowhome in South Philadelphia, the kind built by the thousand a century ago: about sixteen feet wide, a shared wall on each side, a straight staircase in the middle of the plan, a kitchen at the back and a basement under all of it. The owner wanted to keep the house and replace almost everything inside it.
That is a different job from a kitchen or a bathroom. In a rowhome every room depends on the one next to it. The staircase sets where the hallway goes. The kitchen sits against the party wall, so there is only one wall to run plumbing on. The basement decides where a drain can go. If you do the rooms in the wrong order you end up opening finished walls twice.
The plan
We wrote the sequence before we swung a hammer:
- Demolition and structural work, including the old staircase.
- New stair stringers, so the crew had a safe way between floors for the rest of the job.
- Replacement windows, so the house was sealed before drywall.
- Wiring and plumbing with licensed trades, then inspections.
- Drywall, then floors, then kitchen and bathrooms.
- Paint, trim and the finished stair parts last, so nothing got scratched.
- The front door, railings and the back yard at the very end.
Month by month
April. The first floor came down to the studs. The old staircase, worn and steeper than code allows today, came out with it.
May. New stringers went in and we set temporary pine treads so the stair could be used as a work stair. The old window openings got new vinyl replacement windows. Drywall went up on the first floor.
June. Vinyl plank flooring went down across the first floor in one continuous run from the front room to the kitchen, which makes a narrow house feel wider than it is. Drywall was finished and primed.
July. The staircase got its finished oak treads, painted white risers, an oak newel and handrail, and iron balusters. The kitchen cabinets were installed. Out back the crew built a cedar privacy fence with a matching planter box and stained both.
August. Quartz counters and the tile backsplash finished the kitchen. Both bathrooms were tiled and fitted. The basement was carpeted, with a drop ceiling and louvered closet doors. The front got a new entry door with an oval glass panel and new iron railings. Final paint throughout.
What changed for the owner
The house went from a dark, chopped-up floor plan to an open first floor with an electric fireplace wall, a kitchen with storage to the ceiling, two bathrooms that are finished the same way instead of one new and one old, and a basement that is usable living space instead of storage. Outside, the black-framed windows and the fence changed how the house reads from the street and from the yard.
Three lessons for rowhome owners
Fix the stairs first, not last. Everyone wants to start with the kitchen. The stairs are the one thing that touches every floor, and a new staircase is far easier to build in an empty house.
Check the basement before you finish anything. We looked at the walls and the floor for moisture before the rest of the plan was set. If a basement needs drainage work, it needs it before carpet and drywall, not after.
Order windows and doors early. Replacement windows for old masonry openings are made to size and can take weeks. We measured in April so they were on site when the drywall crew needed the house sealed.
See the parts of this project
The staircase, the kitchen and the two bathrooms each have their own write-up with more photos. The links are below.
Finished
The result
South Philadelphia, PAAug 2025after
South Philadelphia, PAAug 2025after
South Philadelphia, PAAug 2025after
South Philadelphia, PAAug 2025after
South Philadelphia, PAAug 2025after
South Philadelphia, PAAug 2025after
South Philadelphia, PAAug 2025after
South Philadelphia, PAAug 2025after
South Philadelphia, PAAug 2025after
South Philadelphia, PAAug 2025after
South Philadelphia, PAAug 2025after
South Philadelphia, PAAug 2025after
South Philadelphia, PAAug 2025after
South Philadelphia, PAAug 2025after
South Philadelphia, PAAug 2025after
South Philadelphia, PAAug 2025after
South Philadelphia, PAMay 2025after
South Philadelphia, PAAug 2025afterIn progress
How it got there
South Philadelphia, PAJul 2025during
South Philadelphia, PAMay 2025during
South Philadelphia, PAJul 2025during
South Philadelphia, PAJul 2025during
South Philadelphia, PAMay 2025before
South Philadelphia, PAMay 2025during
South Philadelphia, PAAug 2025during
South Philadelphia, PAApr 2025before
South Philadelphia, PAMay 2025during
South Philadelphia, PAJun 2025during
South Philadelphia, PAMay 2025before
South Philadelphia, PAJun 2025before
South Philadelphia, PAJul 2025during
South Philadelphia, PAJul 2025duringMore projects
Related work
South Philadelphia, PAAug 2025afterRowhome staircase rebuilt from the stringers up, South Philadelphia
South Philadelphia, PA · May to August 2025
South Philadelphia, PAAug 2025afterRowhome kitchen remodel: white shaker cabinets and quartz, South Philadelphia
South Philadelphia, PA · July to August 2025
South Philadelphia, PAAug 2025afterTwo bathrooms in one rowhome: a tiled tub bath and a glass shower, South Philadelphia
South Philadelphia, PA · May to August 2025
South Philadelphia, PAAug 2025afterFinishing a rowhome basement: carpet, drop ceiling and closets, South Philadelphia
South Philadelphia, PA · August 2025
South Philadelphia, PAAug 2025afterReplacement windows, a new front door and iron railings on a brick rowhome, South Philadelphia
South Philadelphia, PA · May to August 2025
South Philadelphia, PAAug 2025afterVinyl plank floors through a whole rowhome, South Philadelphia
South Philadelphia, PA · June to August 2025
South Philadelphia, PAAug 2025afterCedar privacy fence, planter and patio behind a South Philadelphia rowhome
South Philadelphia, PA · July to August 2025

Free estimate
Have a house like this one?
Send a few lines or call. We will set a time to walk through the house and you will have a written, itemized estimate a few days later.
Monday to Friday, 7:00 am to 5:00 pm